WILMINGTON, NC (WWAY) — You may have noticed construction at a halt lately at the site of a new hotel at 2nd and Grace Streets downtown.

After two weeks of a stand still, construction started back up on the Courtyard by Marriott this week, according to Graham Construction.

Project Manager Eugene Jackson says the two-week delay was due to issues with plumbing, storm drainage and getting the proper safety forms for construction.

Though it seems like not much has been accomplished, Jackson says most of work has been done underground, so there’s a lot that we don’t see.

“We’ve got $1.5 million in the ground that you can’t see, so we’ve got a lot of costs in the ground,” Jackson said. “We’ve got like 231pilings in the ground. It’s a lot.”

The hotel has been under construction for a little more than a year. Jackson says the project is running about 30 days behind schedule.

The entire structure should be finished by the end of the year, and jackson says the hotel is expected to be up and running by the end of March.

Comment on this Story

Related News

McDonald's is recalling STEP-iT fitness trackers distributed in Happy Meals during summer 2016. (Photo: McDonald's)
1 day ago
0 Comments for this article
McDonald’s recalls millions of Happy Meals fitness bands
Read More»
China_USA
2 days ago
0 Comments for this article
WHY IT MATTERS: China
Read More»
Pfizer
2 days ago
0 Comments for this article
Pfizer buying Medivation in deal valued at about $14B
Read More»