Downtown hotel work resumes after two-week delay

READ MORE:
hotelwork.jpg

WILMINGTON, NC (WWAY) -- You may have noticed construction at a halt lately at the site of a new hotel at 2nd and Grace Streets downtown.

After two weeks of a stand still, construction started back up on the Courtyard by Marriott this week, according to Graham Construction.

Project Manager Eugene Jackson says the two-week delay was due to issues with plumbing, storm drainage and getting the proper safety forms for construction.

Though it seems like not much has been accomplished, Jackson says most of work has been done underground, so there's a lot that we don't see.

"We've got $1.5 million in the ground that you can't see, so we've got a lot of costs in the ground," Jackson said. "We've got like 231pilings in the ground. It's a lot."

The hotel has been under construction for a little more than a year. Jackson says the project is running about 30 days behind schedule.

The entire structure should be finished by the end of the year, and jackson says the hotel is expected to be up and running by the end of March.

Disclaimer: Comments posted on this, or any story are opinions of those people posting them, and not the views or opinions of WWAY NewsChannel 3, its management or employees. You can view our comment policy here.

»

Reply

The content of this field is kept private and will not be shown publicly.
  • Web page addresses and e-mail addresses turn into links automatically.
  • Lines and paragraphs break automatically.

More information about formatting options

To prevent automated spam submissions leave this field empty.
CAPTCHA
Please re-enter the code shown in the image below.