NEW HANOVER COUNTY, NC (WWAY) — A pair of new fire stations will be ready to go by 2025.
A station in Castle Hayne is on schedule to wrap up design and bidding the construction in March 2024. Construction will begin in May 2024 and be complete by June 2025. The station should be ready to occupy around July 2025.
A second location on Gordon Road has a site plan completed and on the way. The current schedule has crews wrapping up design and bidding the construction in April 2024. Construction will begin in June 2024 and be complete by July 2025. The station should be ready to occupy around August 2025.
The Gordon Road Fire Station is a brand new location. The Castle Hayne Fire Station is a replacement for the one currently in the area but is older and not in an ideal location, a spokesperson says.